A battery electric tiltrotor programme from Archer Aviation. Published performance figures remain subject to the evidence and conditions below.
Variant: Midnight · Reviewed 14 Sept 2026
AAM International · See source page · Downloaded from the source page and resized to WebP.All numbers retain their evidence label and measurement context. Maximum, typical mission and demonstrated ranges are separate fields.
Approvals are recorded for this variant and authority. A test flight, company approval or target date is not a type certificate.
Year-end marker for a year-only commercial pilot programme target published March 2026; dependent on approvals. Not an exact promised start date.
Archer AviationMLIT confirms acceptance of the type-certification application. Technical assessment and FAA coordination follow; acceptance is not certification.
MLIT / JCABDemonstration flight event, not certification or scheduled passenger service.
Archer AviationAgreement on a certification approach; no issued restricted type certificate established by this announcement.
Archer AviationManufacturer reports acceptance of all means of compliance. This does not mean all compliance testing is complete.
Archer AviationYear-end marker for the late-2024 target published in December 2022. Subsequent 2026 updates still describe certification work; this target was not achieved on the original schedule.
Past target · achievement has not been reconfirmed.
Archer / ICAOArcher AviationReviewed 14 Sept 2026. Publication dates refer to source documents; undated pages may change. Targets are not guarantees.
Historical manufacturer targets: four passengers and pilot, 150 mph maximum, 100 miles maximum, typical 20-mile trips. Older certification targets were superseded.
Midnight development; FAA means of compliance acceptance; planned 2026 passenger flights; liquidity is not funding raised
Official acceptance of Midnight M001 application; prior SD-05, S4, VC2-1 and VX4 applications listed.
July 30 Salinas–Monterey demonstration flights.
Restricted type certification pathway; no issued aircraft certificate announced.